We are delighted to say that the work on our school swimming pool is now completed and we are open for business. The pool is used by school chil...
After many months of waiting the arches are now in place. All of this happened in one day today!!! Enclosure should be complete within 7 d...
After a few weeks wait we are pleased to see that the extension to the plant room is moving forwards. In order to incorporate the new (much larg...
The lorry arrived in school today and poured tonnes of cement around the pool to create the base.
The area surrounding the swimming pool has now been cleared and levelled out. Over the next few days, concrete will be poured around the pool to...
Work begins on installing a gas main, an additional water supply and improved foul drainage. This has involved digging a large trench (approxima...
In order to prepare for an increase in bather load (using the pool lots more than we do at present!) it has been necessary to install new skimmers and...
This is the final stage of the groundworks. The pipes are reaching their final destination outside the ICT room. &...
Today workmen arrived on site to begin preparing the ground for the swimming pool developments. Click on a photo to play a slideshow.